NAME OF PROPONENT |
Permit Description |
PERMIT NO |
DATE ISSUED |
DATE EXPIRED |
DOMINION OILFIELDS SERVICES LTD |
To continue the production and supply of industrial gases and rental of offshore containers |
CI0022780130 |
January 25,2017 |
January 20,2020 |
DRILL-QUIP GHANA LTD |
To commence operation of an Engineering workshop |
CI0040210102 |
February 7, 2017 |
August 6, 2018 |
BELMET 7, TAKORADI PORT |
To continue operations of a fabrication yard |
CE0049160103 |
January 23, 2017 |
January 20, 2019 |
SRI EMAS LIMITED |
To operate a marine supply/storage facility within the Takoradi port |
CI0039850104 |
February 6, 2017 |
August 5, 2018 |
Springfield E&P |
Environmental Permit Form PO1: Proposed 3D marine seismic acquisition in the west cape three points block 2 |
CE0060290103 |
January 4,2017 |
April 3,2017 |
ENI GHANA |
Permit renewal for installation and commissioning of infrastructure for the offshore cape three point (OCTP) block phase-I development |
CE00217801179 |
February 1, 2017 |
July 30, 2018 |
SKAM CONSTRUCTION & ENGINEERING |
To continue operations of An engineering workshop and parking yard |
CI0028900105 |
January 20, 2017 |
January 20, 2019 |
Tullow Ghana |
To continue operations in the jubilee unit area |
CE18280474 |
May 26,2016 |
May 25,2018 |
Tullow Ghana |
To undertake recovery and replacement of the J-09 jumper in the jubilee fields |
CE18280486 |
March 22,2016 |
March 23,2016 |
Tullow Ghana
|
To commence hydrocarbon production and associated commissioning operations in the TEN fields
|
CE18280518
|
June 30,2016
|
June 31,2017
|
Tullow Ghana |
To undertake FPSO spread mooring project at the jubilee fields
|
CE0018280542 |
November 21,2016 |
November 20,2018 |
Tullow Ghana |
EMP:Fabrication yard at the Sekondi naval base |
CE0018280553 |
December 20,2016 |
December 19,2018 |
Tullow Ghana |
To undertake 4D marine seismic acquisition in the jubilee unit area and the teak development area |
CE0018280554 |
December 30,2016 |
April 29,2017 |
ENI GHANA |
To undertake the drilling of five (5) additional development wells in the OCTP Block as per attached schedule. |
CE00217801158 |
May 27,2016 |
April 15,2017 |
GHANA NATIONAL GAS |
Hydrotest Permit for the construction of a 75 km, 20" pipeline PRMS from Esiama to Prestea |
CE0031560389 |
February 17,2016 |
July 30,2016 |
GHANA NATIONAL GAS |
Renewal of Permit for construction and Operation of Loading Gantry at Anochie in the Ellembelle district of the W/R |
CE0031560399 |
May 5,2016 |
November |
GHANA NATIONAL GAS |
To commence the tie-in of the 1.8km gas pipeline from the Ghana Gas Metering Station to the WAPCo R&M Station at Aboadze |
CE0031560420 |
August 18,2016 |
November 17,2016 |
GHANA NATIONAL GAS |
To commence the construction of onshore mainline compressor station at Anokyi and associated facilities at Takoradi Regulatory & Metering Station (TRMS) |
CE0031560434 |
September 26,2016 |
March 20,2018 |
GOSCO |
To commence 3D Marine seismic acquisition in the east Keta block |
CE0059520103 |
November 24,2016 |
May 23,2017 |
CAPE 3 SERVICES LTD |
To continue operation of a logistical base warehouse for the storage of pipelines |
CE0026630104 |
September 5,2016 |
September 4,2018 |
M-I HOLDINGS(BVI) LTD |
To continue to operate a liquid mud plant, environmental solutions and well bore productivity workshop and a chemical warehouse |
CI0019490114 |
August 4,2016 |
August 3,2019 |
KARIBA ENGINEERING SERVICES LIMITED |
To commence construction of engineering and fabrication workshop as per the attached schedule |
CE0055860103 |
April 27,2016 |
April 9,2017 |
INDEPENDENT OIL TOOLS GHANA LTD |
To continue operation of an oil facility to stock and lease oil drilling equipment. |
CE0020570117 |
August 4,2016 |
August 3,2018 |
AOS ORWELL GHANA LTD |
To continue operation of an engineering workshop at new Amanful |
CI0027500105 |
August 23,2016 |
August 22,2018 |
CAPE 3 SERVICES LTD |
To continue operation of a logistical base warehouse for the storage of pipelines |
CE0026630104 |
September 5,2016 |
September 4,2018 |
OMNI ENERGY |
To continue operations of a Sling Fabrication Shop at Takoradi |
CE0042410111 |
September 27,2016 |
September 26,2018 |
SEAWELD TANK SERVICES |
To commence operation of a Tank Service at No.5 Cape Coast, Takoradi |
CI00039140103 |
October 7, 2016 |
October 6, 2018 |
BLUE OCEANS |
To commence installation and operation of the FSU as per attached schedule |
CE0022950119 |
July 25,2016 |
January 25,2018 |
BAYFIED OIL SERVICES |
To continue the operation of the proposed cargo caring storage terminal project as per the attached schedule |
CI0033040102 |
April 11,2016 |
October 10,2017 |
OILFIELD MACHINE SHOP |
To continue operations of an Engineering Workshop |
CI0058760106 |
December 21, 2016 |
June 20, 2018 |